This week I met the supervisor onsite to ask him some questions and go over the site with him. This was our second supervisor, as management changed them the week prior. The site meeting took place on the day the roof tiles went up. The entire roof and pointing was completed in one day.
Later in the week somebody had decided they liked some of the windows and removed them. They left no damage, it was like they were never there.
The two photos with the red crosses are where the windows were taken from.
The bricks had been delivered, and these had us scratching our heads at first. We said to each other 'I remember these looking different, although it has been about six months since we chose them, they don't look right'. EDIT 21/4, OK it was really only me who was looking at the back of the bricks.
It took a couple of days for me to realise that we were looking at the back of them on the pallets! Bit silly of us, and I only realised this when I pulled one out from the pallet on another visit.
The house got wrapped in sisalation later this week, and the plumbers came in to install the gas and water pipes. Again, this was something that seemed to happen really fast in between our visits.